NATIONAL ROUTE 1’S BRIDGES, QUANG NGAI, BINH DINH, AND NATIONAL ROUTE 19C’S BRIDGES, BINH DINH RENOVATION PROJECT
Construction Contractor | Vinh Hung Trading, Consulting, and Construction JSC - Tuan Linh Technology Development and Construction JSC Joint Venture |
Project location | National Route 1, Quang Ngai, Binh Dinh, and National Route 19C’s bridges, Binh Dinh |
Total length | |
Total investment | VND 12,717,371,569 |
Investor | Project Management Unit 4 |
Thầu chính | |
Vinh Hung’s products supplied | Vinh Hung renovation construction : Gach Bridge Km1101+695 (National Route 1) , Quy Thuan Bridge Km1126+625 (National Route 1) , Gia An Bridge Km1127+655 (National Route 1) , Suoi Trinh Bridge Km35+850 (National Route 19C) |
Description project
The renovation work for bridges on National Route 1, Quang Ngai and Binh Dinh province, and bridges on National Route 19C, Binh Dinh is a project in the Construction Bidding package No. 2, invested by the Directorate for Roads of Vietnam. The project has a total investment of VND 12,717,371,569 from the funding source for road economic activities (Government Budget). Implementation time: 210 days from the date of handing over the site with construction solutions:
- Repairing and expanding the traffic range, paving hot asphalt concrete mats on the bridge deck and bridge end roads;
- Reinforcement of span structure with external PC strands combined with carbon fiber bonding;
- Repairing and reinforcing steel beams by reinforcement welding the structure, repairing damage;
- Safety traffic system construction.