LE VAN LUONG TUNNEL WATERPROOF PROJECT
Nhà thầu thi công | Cienco4 Group Joint Stock Company - Fecon Joint Stock Company - Vinh Hung Trading, Consulting and Construction Joint Stock Company |
Vị trí dự án | Hanoi City |
Tổng chiều dài toàn tuyến | 475 m (in which the closed tunnel is 95 m long, the open tunnel and the ledge leading to the closed tunnel are 380 m long) |
Tổng mức đầu tư | 698 billion |
Chủ đầu tư | Traffic Construction Investment Project Management Board of Hanoi City |
Thầu chính | Joint Venture between Cienco4 Group Joint Stock Company - Fecon Joint Stock Company - Vinh Hung Trading, Consulting and Construction Joint Stock Company |
Vĩnh Hưng cung cấp sản phẩm | Vinh Hung provides and constructs a full package of tunnel waterproofing project. |
Description project
Le Van Luong underpass – Ring Road 3 project is a project belong to group B, invested by the Traffic Construction Investment Project Management Board of Hanoi City. The tunnel has a reinforced concrete structure with 475m long, of which the closed tunnel is 95m long, the open tunnel and the barrier leading to the closed tunnel are 380m long (190m on each side). The cross-section is designed with two separate tunnels, each tunnel has 7.75m wide, 2 lanes for traffic in each direction, each lane is 3.5m wide; cut the pavement on both sides to widen Le Van Luong street with about 315m long; cut two sides to widen To Huu Street with about 390m long... The total investment of this project is 698 billion VND from the capital of Hanoi City. Implementation time is about 18 months from the commencement date.