Nhat Le 2 Bridge
Construction subcontractor | 12-CIENCO1 Bridge JSC and Railway Construction Corporation JSC |
Project location | Quang Binh Province |
Total area | |
Total investment | 936.59 billion VND |
Investor | Central Vietnam Corporation |
Main contractor | 12-CIENCO1 Bridge JSC and Railway Construction Corporation JSC |
Vinh Hung supplies product | Cables, bridge bearings and expansion joints |
Description project
Nhat Le 2 Bridge is designed in accordance with the construction scale of new permanent bridge with reinforced concrete and prestressed reinforced concrete. The project includes a main bridge and an access road with a total length of 2,298.7 m, of which the main bridge is 515.2 m long; The whole bridge width of 23.6 m, including 4 vehicle lanes, combined with the cable-stayed main span and approach spans made from Super-T prestressed reinforced concrete. The total investment is VND 936.5 billion, from government bonds and other capital sources. The project implementation period is 36 months from the date of commencement.