VI / EN
Vĩnh Hưng đẩy mạnh thi công gói thầu EX6,EX7 thuộc dự án đường cao tốc Hà Nội - Hải Phòng - Vinh Hung JSC

News

VINHHUNG BOOSTS UP CONSTRUCTION OF PACKAGE EX6. EX7 OF HANOI-HAI PHONG HIGHWAY

14/09/2015 00:00:00
Package EX-6 and EX-7 belonging to the highway project of Ha Noi- Hai Phong, with the Investor of Vietnam Infrastructure Development and Financial Investment Corporation (VIDIFI) and General Contractor of Engineering and Construction Corporation (GS E&C - Korea) is a nationally key traffic project of big scale initiating the BOT model (Build-Operation- Transfer) with an international standard length of 105.5 km.

Package EX-6 and EX-7 belonging to the highway project of Ha Noi- Hai Phong, with the Investor of Vietnam Infrastructure Development and Financial Investment Corporation (VIDIFI) and General Contractor of Engineering and Construction Corporation (GS E&C - Korea) is a nationally key traffic project of big scale initiating the BOT model (Build-Operation- Transfer)  with an international standard length of 105.5 km.

With experience and reputation on market of supplying materials of various kinds for bridge and road work as well as management capacity, construction organization of the key traffic projects such as Ha Noi – Lao Cao highway, Southern coastal corridor project, rehabilitation of Highway no.1…Vinhhung continues to receive the Investor’s and main Contractor’s trusts to become the subcontractor to supply and install the expansion joints for two these packages.  

Package EX-7 commenced on Feb 14th 2009 at Quang Trung comnune, An Lao district, Ha Phong city. The package with the length of 9.3km and the starting point from Km72 +000 to Km81+300 traverses Thanh Ha District, Hai Duong Province and An Lao District, Hai Phong city. There are 02 big bridges Thanh An ad Ba La over the river at this package.

Packge EX-7

Package EX-6 kicked off on Oct 08th 2011 ai Thanh Cuong commune, Thanh Ha District, Hai Duong Province with the section from km 63+300 to km 72 and the total length of 8.7km traversing 5 communes of 02 districts Thanh Tri and Tu Ky (Hai Duong). The section consists of 06 bridges including 02 viaducts, 12 civil underground culverts in which this drainage system is connected to the frontage roads to create a local traffic system along the highway, 01 interchange.

The Ha Noi- Hai Phong highway after completed should create an arterial route linking the localities on the route, ensuring the increasing traffic demands, shorting the travelling time in Ha Noi and the northwestern provinces to Ha Phong city, exploiting the highest potential, promoting socio-economic development.

With the capacity of construction organization, Vinhhung commits to coordinate with the Investor and other Contractors to put the Work into operation by the end of 2015 as directed of the Prime Minister and Minister of Transportation Ministry. The remaining items are urgently organized to finalize, the EX7 package has basically completed the related item, EX6 is in progress of completion. Vinhhung Site Management Board Hung committes to ensure the quality, progress, safety and efficiency to contribute to opening the whole route.

Previously, Vinh Hung was also a supplier of expansion joints and other materials for EX1B, EX5 packages at the Hanoi - Hai Phong Expressway Project and was highly appreciated by the General Contractor as Engineering and Construction Corporation (GS E&C - Korea) and Investor.

Some images of the project