Client
Project Management Unit No. 2
Vinh Hung completed the installation of nearly 13,000 sound-absorbing noise barrier panels, 4,200 screw piles, and 2,500 H-posts along the 40-km National Highway 45 – Nghi Son Expressway. The installations were distributed across 17 locations in residential areas to mitigate traffic noise impacts and improve the living environment for local communities adjacent to the expressway.
Project Management Unit No. 2
Lizen JSC
VND 5.534 trillion
2023